Most of the 35-mile rail corridor is single track with a seven-mile segment of double track. To build this higher-speed Class 6 and 7 track, Herzog crews will use 456,000 lf of continuous welded rail (CWR), 114,450 concrete ties, and over 300,000 tons of ballast. The project also includes the installation of a No.